Tuesday 12 August 2014

A great 2 days aerating on the Priors.

All greens Hollow-tined, dressed with 1.25 ton of sand each and then brushed in.




Monday 4 August 2014

Lots of work taking place in the bunkers at the moment.  Sand top up to some of the worst one's with 3 receiving changes to improve the drainage.  This will be ongoing through the week.

6th Abbotts

We are having a play with shapes on the 9th approach, never believing we have the correct look for the hole.  A complete change in bunker shape is needed with a reduction in the overall size and a lowering of the face but for now this shorter grass surrounding the bunker frames both the bunker and the green.


 Hollow-tining is set for the Priors next week.  Large 3/8 tines will be used with at least 1 ton of sand applied to each green.  The plan will be start on Monday afternoon and continue through Tuesday and Wednesday.

The Abbotts will be Hollow-tined after the Club Championship week beginning September the 8th.